Installation of the pipes and welding of the joints:
From spring 2020 onwards, the pipes and fittings were installed in sections by van den Hooven Rohrleitungsbau in accordance with the construction schedule. The pipes were inserted into the prepared, shored excavations by means of a tower crane or hydraulic excavator and prepared for welding. The mechanical processing of the pipe surface (the peeling) was carried out on the 900 and 1200 mm pipes with a link peeling device from PF-Schweißtechnologie GmbH - Figure 8. Directly after peeling and cleaning the pipe surface, the heating coil sleeves were then pushed on and pulled onto the pipe end by chain hoists - Fig. 9.
Since the heating coil of the large E-muffs is designed as a so-called „bifilar“ coil (two separate welding zones), welding was carried out with two welding machines in parallel in order to keep the processing time as short as possible.